Maintenance of New Facilities

The CSU is scheduled to open 296,528 square feet of new facilities in 2025-26. The cost to fund regular maintenance of these facilities is $23.6 per square foot, for a total of $7 million in 2025-26. Regular maintenance of new facilities includes the cost of utilities, building maintenance, custodial, landscape and administrative support.


Campus Facility # Facility Name
Completion
Date (M-Y)
2025/26 New Space-Square FootageAmount at $23.60/ft1
Dominguez Hills106AOrthotics & Prosthetics SciencesNov-25 5,000 $118,000
Fresno015Engineering EastNov-24 2,265 $53,000
Fullerton008GVisual Arts - Unit GJul-2415,288$361,000
008HVisual Arts - Unit HJul-2437,027$874,000

52,315 $1,235,000
Humboldt177StewartSep-2422,572$533,000
114Engineering & TechnologyMay-2672,783$1,718,000
115Energy Research & Sustainability CenterApr-2617,368410,000
112,723 $2,661,000
San Diego (Calexico)102Brawley Science & EngineeringJul-25 40,789 $963,000
San Luis Obispo065University UnionSep-2314,084$332,000
113Sierra Madre HallSep-233,198$75,000
010TLibrary SurgeSep-234,851$115,000
042ETennis ClubhouseJul-24358$8,000
074John Madden Football CenterSep-234,253$100,000
159Plant Sciences ComplexNov-2521,800$515,000
165Animal Health CenterNov-2520,440482,000
68,984 $1,627,000
San Marcos038FUniversity Village DiningJun-26
2,512 $59,000
Stanislaus (Stockton)002Acacia Replacement BuildingJun-25 11,940 $282,000
Total 296,528 $6,998,000