Description:
Bid proposal packages include:
- Form 700.04 - Notice to Contractors,
- Form 700.05 - Bid Proposal Form,
- Form 702.03 - Certification,
- Form 701.06 - Bid Proposal Form Signature Page,
- Form 702.09A - Bidders Bond-702.09A (for Design-Build project bids only),
- Form 701.05 - Noncollusion Declaration,
- Form 701.09 - Small Business Preference,
- Form 701.08 - Certificate of Appropriate License, DIR Public Wks Reg. and CA Company,
Should contractor have listed a subcontractor when submitting its proposal, then the contractor shall also include the appropriate subcontractor listing document from the list below:
- List of Subcontractors Additional Information-701.04A (for Design-Bid-Build)
- List of Subcontractors for DB and CDB Projects-701.04A.DB/CDB
- List of Subcontractors for CM at Risk Projects-701.04A.CM and DVBE forms-DVBE-T, DVBE-1, DVBE-2, DVBE Declarations form-STD 843).
Confirm Proposer License/DIR Reg: Bid proposal packages are assembled and numbered by the campus bidding office. Prior to issuing a bid proposal package, the Campus bidding office must confirm that bidder is registered with DIR to bid public works projects, appropriately licensed by CSLB, and prequalified with CSU. The campus confirms bidder"s prequalification status during the RFQ process, therefore, campus may then issue a bid/fee proposal package to the shortlisted proposer. Campus shall not post bid/fee proposal packages online without the ""Sample"" overlay on the bid proposal form.
Addenda: If necessary Construction Administrator must issue an addendum to address any deficiency in the bid documents. If addendum contains material changes, it must be distributed not later than 72 hours prior to bid by law (by policy, 5 working days).
References:
- SUAM sections 9731-9731.01; Prep/Contents Bid Documents; E-Bids;
- SUAM sections 9740-9745; Prequalification
- SUAM section 9746; Bid Proposal Package
- SUAM section 9747, Addenda during Bidding
- CM Procedures Manual: sections 7-Prequalification, and 8-Bid & RFP Packages
- PCC section 4104.5 (Late addendum with material changes)
- PCC section 10760 (PQ required of bidders when estimated contract cost exceeds value of a minor cap project, demonstrate experience in performing public works);
- PCC section 10761 (Trustees shall adopt a uniform system of rating bidders, on the basis of standard questionnaires and financial statements, in respect to the size of the contract upon which each bidder is prequalified to bid.)
- PCC section 10764 (bidders must be prequalified to receive a bid proposal package);
- Labor Code section 1725.5 (contractor must register with DIR prior to bidding public works contracts.)
Forms/Templates:
Contractor"s prequalification approval letter is generated by PlanetBids Prequalification Module database, once contractor"s application is approved by the Chancellor"s Office Prequalification Coordinator. Contractor has access to download letter and send to campus as evidence of its prequalification status. (check links on http://www.calstate.edu/cpdc/cm/contractor_prequal_bidders.shtml)