Description:
Attendees: Construction Administrator (CA), Campus Reps, and others as needed)
Discuss preparing documents for advertising and bidding project; i.e. select delivery method, project schedule, phasing, select RFQ/RFQ review committee, etc. Prepare RFQ/RFQ documents to include sufficient information for contractors to respond to RFQ/RFP: Division 1, Contract General Conditions, Supplementary General Conditions, calendar of events, such as date and time that: RFQ responses are due; RFQ shortlist is published, RFP responses are due; distribution of RFQ and RFP, advertising dates, contract duration, liquidated damages, job walkthrough and contractor license requirements. contractor license, liquidated damages, addenda, insurance, etc. It is important to note in the schedule the date for the BOT approval of Schematic Design.
Prior to seeking approval to proceed to bid, the Construction Administrator shall carefully review the project budget, Bid Proposal Form and advertisement. Construction Administrator shall then compile the prebid approval package for Department Director/AVP or VP Administration"s careful review and approval to proceed to bid the project.
References:
- State Administrative Manual (SAM), section 6872;
-
SUAM sections 9721-9721.10;
-
CM Procedures Manual (CA), section 3, Prebid;
-
Bus & Prof Code, sections 7056(A), 7057(B), 7058(C),
-
Contractors State License Board Regulation 832
Forms/Templates:
Approval to Proceed to Bid, Statement of Finances Prior to Bid, Prevailing Wage Cover Page, Prebid Meeting Agenda (700.01), Temporary Facilities Checklist (700.03), Construction Bid Information form (700.02-used for architect front-end letter), the advertisement (Notice Inviting Bids-700.06), and putting together the Bid/Fee Proposal Package, see Prepare bid packages for distribution.